Storm overflow register · South West Water

Okehampton sewage works: storm overflow spills 2025

Okehampton sewage treatment works, run by South West Water, has 2 monitored storm overflows discharging to River Okement(S). In 2025 they recorded 145 spills totalling 1,276 hours, against 169 spills and 1,422 hours in 2024. By hours spilling, it ranks 83 of 334 South West Water works, where 1 spilled longest.

Works size: 9,053 population equivalent (OKEHAMPTON STW, UWWTD 2018). Used for the spill volume estimate.

Every spill in 2025

Each blue mark is one spill, placed by when it started and sized by how long it lasted. Hover over a mark for the date and duration.

JanFebMarAprMayJunJulAugSepOctNovDecOkehampton STW1 Jan 2025 12:23 GMT, 3.1 h1 Jan 2025 20:48 GMT, 10 min4 Jan 2025 23:42 GMT, 105 min5 Jan 2025 02:50 GMT, 35 min5 Jan 2025 03:28 GMT, 100.7 h9 Jan 2025 09:16 GMT, 41 min9 Jan 2025 11:48 GMT, 15 min9 Jan 2025 12:34 GMT, 63 min9 Jan 2025 14:23 GMT, 11 min10 Jan 2025 09:28 GMT, 6.9 h10 Jan 2025 17:06 GMT, 3.2 h10 Jan 2025 20:27 GMT, 41 min24 Jan 2025 03:30 GMT, 3.8 h24 Jan 2025 09:33 GMT, 17 min24 Jan 2025 21:29 GMT, 32 min24 Jan 2025 22:17 GMT, 35 min26 Jan 2025 10:49 GMT, 108.5 h31 Jan 2025 03:03 GMT, 12.2 h31 Jan 2025 19:05 GMT, 2.2 h21 Feb 2025 12:24 GMT, 3.1 h23 Feb 2025 15:36 GMT, 43.8 h25 Feb 2025 11:29 GMT, 8 min25 Feb 2025 11:39 GMT, 12.2 h26 Feb 2025 05:18 GMT, 23.8 h27 Feb 2025 05:40 GMT, 10 min27 Feb 2025 06:47 GMT, 9.8 h27 Feb 2025 16:42 GMT, 6 h15 Apr 2025 16:24 GMT, 80 min15 Apr 2025 18:04 GMT, 3.3 h15 Apr 2025 22:08 GMT, 25.5 h18 Apr 2025 12:04 GMT, 116 min18 Apr 2025 15:06 GMT, 28.5 h27 May 2025 11:15 GMT, 4.4 h27 May 2025 16:43 GMT, 2.1 h27 May 2025 23:36 GMT, 17 min12 Jun 2025 08:40 GMT, 11.4 h12 Jun 2025 20:16 GMT, 5 min13 Jun 2025 15:29 GMT, 29.8 h14 Jun 2025 21:27 GMT, 18 min14 Jun 2025 21:51 GMT, 9 min14 Jun 2025 22:19 GMT, 9 min29 Aug 2025 00:53 GMT, 37 min3 Oct 2025 21:02 GMT, 113 min20 Oct 2025 12:42 GMT, 79 min20 Oct 2025 18:28 GMT, 22 min20 Oct 2025 19:55 GMT, 34 min24 Oct 2025 18:13 GMT, 2.8 h25 Oct 2025 02:13 GMT, 22 min26 Oct 2025 22:14 GMT, 13 min27 Oct 2025 16:57 GMT, 22 min28 Oct 2025 06:11 GMT, 26 min29 Oct 2025 09:59 GMT, 15 min29 Oct 2025 10:17 GMT, 2.5 h29 Oct 2025 14:37 GMT, 32 min30 Oct 2025 21:13 GMT, 2.2 h31 Oct 2025 13:08 GMT, 113 min31 Oct 2025 20:23 GMT, 75 min31 Oct 2025 22:18 GMT, 41 min2 Nov 2025 01:01 GMT, 2 h2 Nov 2025 04:52 GMT, 79 min2 Nov 2025 10:22 GMT, 3.3 h2 Nov 2025 13:51 GMT, 8 min3 Nov 2025 12:06 GMT, 18 min4 Nov 2025 15:14 GMT, 6.9 h5 Nov 2025 00:51 GMT, 4.2 h5 Nov 2025 05:07 GMT, 35 min5 Nov 2025 06:17 GMT, 6.1 h8 Nov 2025 05:05 GMT, 52 min9 Nov 2025 14:15 GMT, 2.7 h9 Nov 2025 17:03 GMT, 4.7 h10 Nov 2025 09:18 GMT, 3 h10 Nov 2025 17:22 GMT, 51 min11 Nov 2025 10:47 GMT, 52 min11 Nov 2025 12:01 GMT, 66 min11 Nov 2025 16:54 GMT, 93.2 h15 Nov 2025 14:23 GMT, 7 h16 Nov 2025 11:23 GMT, 3.9 h16 Nov 2025 15:20 GMT, 21 min16 Nov 2025 15:48 GMT, 6 min16 Nov 2025 16:55 GMT, 4.3 h18 Nov 2025 14:52 GMT, 44 min18 Nov 2025 16:12 GMT, 23 min24 Nov 2025 09:22 GMT, 81 min24 Nov 2025 15:32 GMT, 7 min24 Nov 2025 15:44 GMT, 9 min27 Nov 2025 18:40 GMT, 56 min29 Nov 2025 02:34 GMT, 4.8 h29 Nov 2025 10:07 GMT, 69 min29 Nov 2025 11:32 GMT, 56 min30 Nov 2025 22:36 GMT, 4 h1 Dec 2025 03:34 GMT, 64 min1 Dec 2025 05:01 GMT, 12 min1 Dec 2025 06:18 GMT, 90.2 h5 Dec 2025 00:49 GMT, 47 min5 Dec 2025 09:08 GMT, 102 min5 Dec 2025 11:12 GMT, 159.1 h12 Dec 2025 02:32 GMT, 21.6 h13 Dec 2025 09:56 GMT, 3.5 h15 Dec 2025 03:42 GMT, 100 min15 Dec 2025 05:44 GMT, 33 min15 Dec 2025 06:34 GMT, 46 h17 Dec 2025 07:46 GMT, 5.8 h17 Dec 2025 18:14 GMT, 58 h20 Dec 2025 09:20 GMT, 4.9 h20 Dec 2025 17:50 GMT, 6.5 h21 Dec 2025 10:59 GMT, 78 min21 Dec 2025 14:41 GMT, 9.5 h22 Dec 2025 01:27 GMT, 25.5 h23 Dec 2025 05:10 GMT, 17.6 hOkehampton STW1 Jan 2025 10:09 GMT, 34 min1 Jan 2025 12:30 GMT, 17 min4 Jan 2025 22:11 GMT, 2 h5 Jan 2025 06:48 GMT, 5 h5 Jan 2025 19:10 GMT, 19.3 h6 Jan 2025 19:17 GMT, 103 min6 Jan 2025 21:14 GMT, 43 min7 Jan 2025 09:36 GMT, 39 min23 Jan 2025 10:47 GMT, 23 min24 Jan 2025 02:04 GMT, 2.3 h24 Jan 2025 05:32 GMT, 22 min26 Jan 2025 09:30 GMT, 18.6 h27 Jan 2025 05:11 GMT, 52 min27 Jan 2025 14:37 GMT, 72 min27 Jan 2025 17:10 GMT, 95 min27 Jan 2025 18:47 GMT, 8 min27 Jan 2025 18:56 GMT, 7 min27 Jan 2025 19:05 GMT, 12 min27 Jan 2025 19:19 GMT, 6 min27 Jan 2025 20:07 GMT, 21 min27 Jan 2025 23:12 GMT, 25 min28 Jan 2025 02:44 GMT, 80 min28 Jan 2025 04:06 GMT, 62 min28 Jan 2025 05:36 GMT, 32 min28 Jan 2025 07:07 GMT, 3.8 h28 Jan 2025 13:19 GMT, 2.1 h21 Feb 2025 10:09 GMT, 14 min21 Feb 2025 12:21 GMT, 4 min23 Feb 2025 18:31 GMT, 80 min23 Feb 2025 19:56 GMT, 5.1 h24 Feb 2025 07:06 GMT, 33 min26 Feb 2025 05:39 GMT, 2.5 h26 Feb 2025 11:15 GMT, 17 min15 Apr 2025 14:35 GMT, 55 min15 Apr 2025 16:11 GMT, 50 min15 Apr 2025 18:16 GMT, 19 min15 Apr 2025 19:17 GMT, 45 min15 Apr 2025 22:13 GMT, 9.2 h21 May 2025 07:00 GMT, 28 min24 May 2025 22:17 GMT, 10 min27 May 2025 09:47 GMT, 38 min27 May 2025 11:32 GMT, 34 min27 May 2025 13:26 GMT, 16 min7 Jun 2025 12:49 GMT, 35 min12 Jun 2025 05:21 GMT, 40 min12 Jun 2025 08:33 GMT, 26 min12 Jun 2025 10:11 GMT, 117 min13 Jun 2025 14:56 GMT, 32 min13 Jun 2025 16:55 GMT, 2.5 h13 Jun 2025 20:59 GMT, 15 min13 Jun 2025 21:33 GMT, 63 min14 Jun 2025 10:49 GMT, 34 min14 Aug 2025 01:15 GMT, 8 min28 Aug 2025 23:07 GMT, 77 min29 Aug 2025 00:36 GMT, 10 min31 Aug 2025 10:11 GMT, 16 min1 Sep 2025 13:18 GMT, 8 min3 Sep 2025 10:18 GMT, 37 min12 Sep 2025 11:45 GMT, 3 min14 Sep 2025 15:05 GMT, 20 min20 Sep 2025 12:45 GMT, 13 min3 Oct 2025 20:06 GMT, 46 min20 Oct 2025 12:35 GMT, 31 min30 Oct 2025 21:42 GMT, 24 min31 Oct 2025 13:11 GMT, 52 min8 Nov 2025 05:09 GMT, 20 min9 Nov 2025 15:01 GMT, 40 min11 Nov 2025 16:59 GMT, 2.2 h11 Nov 2025 19:35 GMT, 6 h12 Nov 2025 02:27 GMT, 22 min12 Nov 2025 03:55 GMT, 9.2 h12 Nov 2025 23:17 GMT, 32 min13 Nov 2025 19:25 GMT, 2.6 h14 Nov 2025 14:20 GMT, 78 min29 Nov 2025 04:04 GMT, 31 min29 Nov 2025 05:24 GMT, 32 min29 Nov 2025 06:33 GMT, 9 min30 Nov 2025 23:33 GMT, 75 min1 Dec 2025 12:21 GMT, 74 min1 Dec 2025 14:39 GMT, 9.5 h4 Dec 2025 03:50 GMT, 35 min4 Dec 2025 10:45 GMT, 33 min5 Dec 2025 14:06 GMT, 30 min5 Dec 2025 14:59 GMT, 119 min5 Dec 2025 17:53 GMT, 27 min6 Dec 2025 10:27 GMT, 53 min6 Dec 2025 17:04 GMT, 13 min7 Dec 2025 10:32 GMT, 59 min8 Dec 2025 23:31 GMT, 25.9 h12 Dec 2025 02:54 GMT, 13 min12 Dec 2025 04:09 GMT, 53 min15 Dec 2025 13:17 GMT, 28 min15 Dec 2025 18:06 GMT, 87 min15 Dec 2025 22:05 GMT, 39 min16 Dec 2025 01:20 GMT, 22 min17 Dec 2025 20:37 GMT, 11 min17 Dec 2025 21:17 GMT, 86 min18 Dec 2025 11:28 GMT, 3.7 h18 Dec 2025 15:21 GMT, 28 min21 Dec 2025 14:53 GMT, 114 min22 Dec 2025 03:12 GMT, 11 min

Estimated spill volume by month, 2025

Hours spilling each month × the estimated spill rate for a works of this size. The bars are central estimates and the whiskers show the low–high range. Method.

050k100k150k200kJan 2025: 313 h spilling ≈ 48,552 m³ (range 19,339–121,892 m³)JanFeb 2025: 109 h spilling ≈ 16,908 m³ (range 6,735–42,448 m³)FebMar 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0–0.0 m³)MarApr 2025: 73 h spilling ≈ 11,262 m³ (range 4,486–28,273 m³)AprMay 2025: 8.9 h spilling ≈ 1,381 m³ (range 550–3,466 m³)MayJun 2025: 50 h spilling ≈ 7,818 m³ (range 3,114–19,627 m³)JunJul 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0–0.0 m³)JulAug 2025: 2.5 h spilling ≈ 388 m³ (range 154–974 m³)AugSep 2025: 1.4 h spilling ≈ 217 m³ (range 87–545 m³)SepOct 2025: 20 h spilling ≈ 3,133 m³ (range 1,248–7,866 m³)OctNov 2025: 184 h spilling ≈ 28,604 m³ (range 11,393–71,811 m³)NovDec 2025: 513 h spilling ≈ 79,622 m³ (range 31,715–199,894 m³)Dec
Cubic metres (m³), estimate. Hours are measured by the event duration monitor.

Longest single spills

Started (GMT)OverflowDurationEstimated volume
5 Dec 2025, 11:12Okehampton STW6.6 days9,827 – 61,939 m³
26 Jan 2025, 10:49Okehampton STW4.5 days6,703 – 42,247 m³
5 Jan 2025, 03:28Okehampton STW4.2 days6,224 – 39,229 m³
11 Nov 2025, 16:54Okehampton STW3.9 days5,757 – 36,288 m³
1 Dec 2025, 06:18Okehampton STW3.8 days5,571 – 35,114 m³

Estimated 2025 spill volume and pollution

Estimate, not a measurement. Monitors record how long an overflow spills, not how much. This calculator back-calculates a spill rate from the size of the works, using the Environment Agency's permit formulae, and multiplies it by published storm-sewage concentrations. How it works.

Volume, central estimate197,853 m³range 78,809 – 496,718 m³
In litres197.9 millionrange 78.8 million – 496.7 million L
Olympic swimming pools79at 2,500 m³ each
Organic load, as people's raw sewage296,780person-days of untreated BOD

Assumed spill rate while spilling: 17.2 – 108.2 L/s (central 43.1 L/s), from a dry-weather flow of 17.2 L/s.

Pollutant releasedLowCentralHighConcentration used (low / typical / high)
BOD₅ (organic load) 3,152 kg17,807 kg99,344 kg 40 / 90 / 200 mg/L
Low/high: Europe range, Ellis & Jenkins 2005; typical: UK, Ellis & Jenkins 2005 (both via botturi)
Suspended solids 8,275 kg84,088 kg358,134 kg 105 / 425 / 721 mg/L
Low/high: Europe range; typical: UK, Ellis & Jenkins 2005 (via botturi)
Ammonium-N 150 kg1,246 kg4,619 kg 1.9 / 6.3 / 9.3 mg/L
Low: Germany, Brombach 2005; typical/high: Paris range 3.3–9.3 midpoint and top, Gasperi 2012 (via botturi); no UK value found
Total phosphorus 95 kg514 kg2,682 kg 1.2 / 2.6 / 5.4 mg/L
Low/high: Paris, Gasperi 2012; typical: Slovakia (via botturi). UK figure of 10 mg/L treated as an outlier
E. coli 7.9 trillion organisms197.9 trillion organisms5.0 × 10¹⁵ organisms 10,000 / 100,000 / 1.0 million per 100 mL
Median range at CSO and retention-tank outlets, Stott et al. 2018 (via botturi); typical = log midpoint

Low combines the low spill rate with low concentrations, and high combines high with high, so the true figure is very likely inside the range. Long spills become more diluted as they go on, so the central figure tends to overstate the load of long events. The calculator does not estimate the effect on the receiving water, which depends on river flow or tide at the time of the spill.

Okehampton STW

Storm tank at sewage works · discharges to River Okement(S)

Spills 2025
87 (1,091 hours) · down 19% on 2024
Spills 2024
107 (1,227 hours)
Long-term average
77.9 spills a year (monitored since 2016)
Monitor uptime
100% of the year
High-spill reason (company)
Performance - SW Infiltration
Investigation
Operational investigation completed
Improvement
No improvement action in reporting period
WFD catchment
Middle River Okement (GB108050008110)
Outlet location
SX60049825 (OS grid reference) · View on Apple Maps
EA ID / permit
SBB00869 · 202463 · company name: HILL BARTON STW_SSO_OKEHAMPTON

Okehampton STW

Inlet overflow at sewage works · discharges to River Okement(S)

Spills 2025
58 (184 hours) · down 6% on 2024
Spills 2024
62 (195 hours)
Long-term average
75.1 spills a year (monitored since 2016)
Monitor uptime
100% of the year
High-spill reason (company)
Not asset maintenance - hydraulic capacity
Investigation
Operational investigation ongoing
Improvement
No improvement action in reporting period
WFD catchment
Middle River Okement (GB108050008110)
Outlet location
SX59879826 (OS grid reference) · View on Apple Maps
EA ID / permit
SBB00868 · 202463 · company name: HILL BARTON STW_SO_OKEHAMPTON

How the estimate works

  1. Dry-weather flow (DWF) = population × water use per person × (1 + infiltration). Water use is 136.5 L per person per day, England's per-capita consumption for 2024–25 [EA]. Infiltration of groundwater into sewers is taken as 0–40% of that flow [Escritt, via HBF]. The Environment Agency defines DWF as PG + I + E [EA].
  2. Population. The size of each works comes from the load entering it as reported under the Urban Waste Water Treatment Directive, in population equivalents (1 p.e. = 60 g of BOD a day) [UWWTD]. We treat population equivalent as population. That overstates flow where trade effluent adds load, and no official source links the two. Works serving fewer than 2,000 p.e. are not reported, so their size has to be entered by hand.
  3. Low spill rate = DWF. This is the method used by Giakoumis & Voulvoulis (2026), which they note likely underestimates storm loads [G&V].
  4. High spill rate = Formula A − flow to full treatment = (DWF + 1360P) − 3DWF. This is the largest flow the permit expects the storm tanks to handle before it passes on to treatment or overflows [EA]. The central rate is the geometric mean of the low and high rates.
  5. Volume = spill rate × hours spilling, with hours taken from the event duration monitor.
  6. Pollution = volume × published storm-sewage concentrations [Botturi et al.] [US EPA]. Organic load is also shown as person-days of untreated sewage at 60 g of BOD per person per day [UWWTD].

What this cannot tell you. It gives no real flow for any single spill, and no effect on the river or sea, which depends on the flow, tide and the other pressures on the water at the time. It gives no figure for spills from overflows on the sewer network, which serve catchments of unknown size. It is a way to put hours into rough physical terms, not a substitute for flow monitoring.

Sources

  1. EA: Water companies – environmental permits for storm overflows and emergency overflows
  2. EA: Water resources 2024 to 2025 – per capita consumption
  3. HBF: Foul sewer design – historic conventions (citing Escritt 1984 on infiltration)
  4. Giakoumis & Voulvoulis (2026), Environ. Sci.: Water Res. Technol., doi:10.1039/D5EW00860C
  5. Botturi et al. (2021), Crit. Rev. Environ. Sci. Technol. 51:1585 – CSO quality review, Table 2
  6. US EPA (2004) Report to Congress on CSOs and SSOs, chapter 4
  7. Urban Waste Water Treatment Directive, Article 2(6): 1 p.e. = 60 g BOD5/day
  8. Olympic-size swimming pool: 2,500 m³ at the nominal 2 m depth

← All South West Water works · Contains Environment Agency data licensed under the Open Government Licence v3.0. Spill start and stop times: © Environment Agency copyright and/or database right 2026. All rights reserved. They are water-company data and have not been verified by the Environment Agency. Works size: EEA Waterbase UWWTD. How to read the data.