Storm overflow register · Yorkshire Water

Hull sewage works: storm overflow spills 2025

Hull sewage treatment works, run by Yorkshire Water, has 1 monitored storm overflow discharging to River Humber. In 2025 it recorded 116 spills totalling 1,560 hours, against 194 spills and 2,499 hours in 2024. By hours spilling, it ranks 16 of 283 Yorkshire Water works, where 1 spilled longest.

Works size: 512,879 population equivalent (HULL STW, UWWTD 2018). Used for the spill volume estimate.

Every spill in 2025

Each blue mark is one spill, placed by when it started and sized by how long it lasted. Hover over a mark for the date and duration.

JanFebMarAprMayJunJulAugSepOctNovDecHull WwTW7 spills, 56 h, 1 Jan to 3 Jan18 spills, 131.3 h, 5 Jan to 12 Jan2 spills, 1.5 h, 24 Jan to 24 Jan11 spills, 77 h, 26 Jan to 30 Jan5 spills, 16.5 h, 10 Feb to 12 Feb24 Feb 2025 01:15 GMT, 6.8 h2 spills, 7.8 h, 26 Feb to 27 Feb2 spills, 6.3 h, 13 Mar to 13 Mar3 spills, 12 h, 22 Mar to 23 Mar15 Apr 2025 10:15 GMT, 10 h21 Apr 2025 17:30 GMT, 6.3 h29 May 2025 10:15 GMT, 9.8 h3 Jun 2025 11:45 GMT, 2 h3 spills, 19.8 h, 5 Jun to 6 Jun4 spills, 7 h, 10 Jun to 10 Jun2 Jul 2025 10:00 GMT, 10.8 h6 Jul 2025 14:45 GMT, 6.5 h7 Jul 2025 20:00 GMT, 3 h2 spills, 12 h, 15 Jul to 16 Jul3 spills, 29.3 h, 19 Jul to 21 Jul3 spills, 15.3 h, 22 Jul to 24 Jul4 Aug 2025 12:00 GMT, 7.3 h2 spills, 2.5 h, 28 Aug to 29 Aug3 spills, 6.3 h, 4 Sep to 5 Sep2 spills, 12.5 h, 11 Sep to 12 Sep8 spills, 26.3 h, 14 Sep to 17 Sep20 Sep 2025 13:30 GMT, 36 h28 Sep 2025 08:30 GMT, 9 h6 spills, 33.8 h, 3 Oct to 4 Oct4 spills, 24.8 h, 19 Oct to 21 Oct23 Oct 2025 02:45 GMT, 19.5 h4 spills, 3.5 h, 25 Oct to 25 Oct31 Oct 2025 18:30 GMT, 2.5 h3 Nov 2025 08:15 GMT, 3.8 h2 spills, 13.3 h, 4 Nov to 5 Nov89 spills, 912.8 h, 10 Nov to 25 Dec

Estimated spill volume by month, 2025

Hours spilling each month × the estimated spill rate for a works of this size. The bars are central estimates and the whiskers show the low-high range. Method.

05M10M15MJan 2025: 266 h spilling ≈ 2.3 million m³ (range 930,406-5.9 million m³)JanFeb 2025: 31 h spilling ≈ 272,425 m³ (range 108,512-683,933 m³)FebMar 2025: 18 h spilling ≈ 159,940 m³ (range 63,707-401,535 m³)MarApr 2025: 16 h spilling ≈ 142,364 m³ (range 56,706-357,410 m³)AprMay 2025: 9.8 h spilling ≈ 86,121 m³ (range 34,304-216,211 m³)MayJun 2025: 29 h spilling ≈ 253,091 m³ (range 100,811-635,396 m³)JunJul 2025: 77 h spilling ≈ 674,910 m³ (range 268,831-1.7 million m³)JulAug 2025: 9.8 h spilling ≈ 86,121 m³ (range 34,304-216,211 m³)AugSep 2025: 90 h spilling ≈ 790,910 m³ (range 315,036-2.0 million m³)SepOct 2025: 84 h spilling ≈ 738,183 m³ (range 294,034-1.9 million m³)OctNov 2025: 459 h spilling ≈ 4.0 million m³ (range 1.6 million-10.1 million m³)NovDec 2025: 471 h spilling ≈ 4.1 million m³ (range 1.6 million-10.4 million m³)Dec
Cubic metres (m³), estimate. Hours are measured by the event duration monitor.

Longest single spills

Started (GMT)OverflowDurationEstimated volume
12 Nov 2025, 05:30Hull WwTW5.6 days473,429 - 3.0 million m³
29 Nov 2025, 05:45Hull WwTW4.0 days333,413 - 2.1 million m³
5 Dec 2025, 04:30Hull WwTW3.6 days301,909 - 1.9 million m³
18 Nov 2025, 13:15Hull WwTW3.4 days288,783 - 1.8 million m³
5 Jan 2025, 04:30Hull WwTW3.2 days269,531 - 1.7 million m³

Estimated 2025 spill volume and pollution

Estimate, not a measurement. Monitors record how long an overflow spills, not how much. This calculator back-calculates a spill rate from the size of the works, using the Environment Agency's permit formulae, and multiplies it by published storm-sewage concentrations. How it works.

Volume, central estimate13.7 million m³range 5.5 million - 34.4 million m³
In litres13.7 billionrange 5.5 billion - 34.4 billion L
Olympic swimming pools5,484at 2,500 m³ each
Organic load, as people's raw sewage20.6 millionperson-days of untreated BOD

Assumed spill rate while spilling: 972.3 - 6,128.4 L/s (central 2,441.1 L/s), from a dry-weather flow of 972.3 L/s.

Pollutant releasedLowCentralHighConcentration used (low / typical / high)
BOD₅ (organic load) 218,425 kg1.2 million kg6.9 million kg 40 / 90 / 200 mg/L
Low/high: Europe range, Ellis & Jenkins 2005; typical: UK, Ellis & Jenkins 2005 (both via botturi)
Suspended solids 573,365 kg5.8 million kg24.8 million kg 105 / 425 / 721 mg/L
Low/high: Europe range; typical: UK, Ellis & Jenkins 2005 (via botturi)
Ammonium-N 10,375 kg86,367 kg320,081 kg 1.9 / 6.3 / 9.3 mg/L
Low: Germany, Brombach 2005; typical/high: Paris range 3.3-9.3 midpoint and top, Gasperi 2012 (via botturi); no UK value found
Total phosphorus 6,553 kg35,644 kg185,853 kg 1.2 / 2.6 / 5.4 mg/L
Low/high: Paris, Gasperi 2012; typical: Slovakia (via botturi). UK figure of 10 mg/L treated as an outlier
E. coli 546.1 trillion organisms1.4 × 10¹⁶ organisms3.4 × 10¹⁷ organisms 10,000 / 100,000 / 1.0 million per 100 mL
Median range at CSO and retention-tank outlets, Stott et al. 2018 (via botturi); typical = log midpoint

Low combines the low spill rate with low concentrations, and high combines high with high, so the true figure is very likely inside the range. Long spills become more diluted as they go on, so the central figure tends to overstate the load of long events. The calculator does not estimate the effect on the receiving water, which depends on river flow or tide at the time of the spill.

Hull WwTW

Inlet overflow at sewage works · discharges to River Humber

Spills 2025
116 (1,560 hours) · down 40% on 2024
Spills 2024
194 (2,499 hours)
Long-term average
93.0 spills a year (monitored since 2020)
Monitor uptime
100% of the year
High-spill reason (company)
Not asset maintenance - hydraulic capacity
Investigation
UWWTR investigation ongoing, Operational investigation completed
Improvement
No improvement action in reporting period
WFD catchment
HUMBER LOWER (GB530402609201)
Outlet location
TA1486028060 (OS grid reference) · View on Apple Maps
EA ID / permit
YWS01451 · WRA7619 · company name: HULL/STW

How the estimate works

  1. Dry-weather flow (DWF) = population × water use per person × (1 + infiltration). Water use is 136.5 L per person per day, England's per-capita consumption for 2024-25 [EA]. Infiltration of groundwater into sewers is taken as 0-40% of that flow [Escritt, via HBF]. The Environment Agency defines DWF as PG + I + E [EA].
  2. Population. The size of each works comes from the load entering it as reported under the Urban Waste Water Treatment Directive, in population equivalents (1 p.e. = 60 g of BOD a day) [UWWTD]. We treat population equivalent as population. That overstates flow where trade effluent adds load, and no official source links the two. Works serving fewer than 2,000 p.e. are not reported, so their size has to be entered by hand.
  3. Low spill rate = DWF. This is the method used by Giakoumis & Voulvoulis (2026), which they note likely underestimates storm loads [G&V].
  4. High spill rate = Formula A − flow to full treatment = (DWF + 1360P) − 3DWF. This is the largest flow the permit expects the storm tanks to handle before it passes on to treatment or overflows [EA]. The central rate is the geometric mean of the low and high rates.
  5. Volume = spill rate × hours spilling, with hours taken from the event duration monitor.
  6. Pollution = volume × published storm-sewage concentrations [Botturi et al.] [US EPA]. Organic load is also shown as person-days of untreated sewage at 60 g of BOD per person per day [UWWTD].

What this cannot tell you. It gives no real flow for any single spill, and no effect on the river or sea, which depends on the flow, tide and the other pressures on the water at the time. It gives no figure for spills from overflows on the sewer network, which serve catchments of unknown size. It is a way to put hours into rough physical terms, not a substitute for flow monitoring.

Sources

  1. EA: Water companies - environmental permits for storm overflows and emergency overflows
  2. EA: Water resources 2024 to 2025 - per capita consumption
  3. HBF: Foul sewer design - historic conventions (citing Escritt 1984 on infiltration)
  4. Giakoumis & Voulvoulis (2026), Environ. Sci.: Water Res. Technol., doi:10.1039/D5EW00860C
  5. Botturi et al. (2021), Crit. Rev. Environ. Sci. Technol. 51:1585 - CSO quality review, Table 2
  6. US EPA (2004) Report to Congress on CSOs and SSOs, chapter 4
  7. Urban Waste Water Treatment Directive, Article 2(6): 1 p.e. = 60 g BOD5/day
  8. Olympic-size swimming pool: 2,500 m³ at the nominal 2 m depth

← All Yorkshire Water works · Contains Environment Agency data licensed under the Open Government Licence v3.0. Spill start and stop times: © Environment Agency copyright and/or database right 2026. All rights reserved. They are water-company data and have not been verified by the Environment Agency. Works size: EEA Waterbase UWWTD. How to read the data.