Wistow sewage treatment works, run by Yorkshire Water, has 2 monitored storm overflows discharging to River Ouse (Tidal). In 2025 they recorded 195 spills totalling 2,744 hours, against 312 spills and 5,160 hours in 2024. By hours spilling, it ranks 3 of 283 Yorkshire Water works, where 1 spilled longest.
Every spill in 2025
Each blue mark is one spill, placed by when it started and sized by how long it lasted. Hover over a mark for the date and duration.
Hours spilling by month, 2025
Longest single spills
| Started (GMT) | Overflow | Duration |
|---|---|---|
| 4 Jan 2025, 10:45 | Wistow Sewage Treatment Works | 15.8 days |
| 1 Jan 2025, 00:00 | Wistow Sewage Treatment Works | 11.3 days |
| 15 Dec 2025, 01:30 | Wistow Sewage Treatment Works | 10.2 days |
| 26 Jan 2025, 04:45 | Wistow Sewage Treatment Works | 8.5 days |
| 4 Dec 2025, 15:30 | Wistow Sewage Treatment Works | 4.4 days |
Estimated 2025 spill volume and pollution
Estimate, not a measurement. Monitors record how long an overflow spills, not how much. This calculator back-calculates a spill rate from the size of the works, using the Environment Agency's permit formulae, and multiplies it by published storm-sewage concentrations. How it works.
This works serves fewer than 2,000 people, or was not matched to a UWWTD report, so its size is not published. The population equivalent above is a placeholder of 1,000. Enter the population served if you know it.
Assumed spill rate while spilling: 1.9 - 11.9 L/s (central 4.8 L/s), from a dry-weather flow of 1.9 L/s.
| Pollutant released | Low | Central | High | Concentration used (low / typical / high) |
|---|---|---|---|---|
| BOD₅ (organic load) | 749 kg | 4,232 kg | 23,609 kg | 40 / 90 / 200 mg/L Low/high: Europe range, Ellis & Jenkins 2005; typical: UK, Ellis & Jenkins 2005 (both via botturi) |
| Suspended solids | 1,967 kg | 19,984 kg | 85,111 kg | 105 / 425 / 721 mg/L Low/high: Europe range; typical: UK, Ellis & Jenkins 2005 (via botturi) |
| Ammonium-N | 36 kg | 296 kg | 1,098 kg | 1.9 / 6.3 / 9.3 mg/L Low: Germany, Brombach 2005; typical/high: Paris range 3.3-9.3 midpoint and top, Gasperi 2012 (via botturi); no UK value found |
| Total phosphorus | 22 kg | 122 kg | 637 kg | 1.2 / 2.6 / 5.4 mg/L Low/high: Paris, Gasperi 2012; typical: Slovakia (via botturi). UK figure of 10 mg/L treated as an outlier |
| E. coli | 1.9 trillion organisms | 47.0 trillion organisms | 1.2 × 10¹⁵ organisms | 10,000 / 100,000 / 1.0 million per 100 mL Median range at CSO and retention-tank outlets, Stott et al. 2018 (via botturi); typical = log midpoint |
Low combines the low spill rate with low concentrations, and high combines high with high, so the true figure is very likely inside the range. Long spills become more diluted as they go on, so the central figure tends to overstate the load of long events. The calculator does not estimate the effect on the receiving water, which depends on river flow or tide at the time of the spill.
Wistow Sewage Treatment Works
Storm tank at sewage works · discharges to River Ouse (Tidal)
- Spills 2025
- 113 (1,879 hours) · down 37% on 2024
- Spills 2024
- 179 (3,158 hours)
- Long-term average
- 107.5 spills a year (monitored since 2020)
- Monitor uptime
- 100% of the year
- High-spill reason (company)
- Not asset maintenance - hydraulic capacity
- Investigation
- UWWTR investigation ongoing, Operational investigation completed
- Improvement
- No improvement action in reporting period
- WFD catchment
- Ouse from R Wharfe to Upper Humber (GB104027064270)
- Outlet location
- SE6055136380 (OS grid reference) · View on Apple Maps
- EA ID / permit
- YWS00405 · 27/24/0228 · company name: WISTOW/STW
Wistow Sewage Treatment Works
Inlet overflow at sewage works · discharges to River Ouse (Tidal)
- Spills 2025
- 82 (865 hours) · down 38% on 2024
- Spills 2024
- 133 (2,002 hours)
- Long-term average
- 105.2 spills a year (monitored since 2020)
- Monitor uptime
- 100% of the year
- High-spill reason (company)
- Not asset maintenance - hydraulic capacity
- Investigation
- Env Act (SODRP) investigation completed, UWWTR investigation completed, Operational investigation completed
- Improvement
- No improvement action in reporting period
- WFD catchment
- Ouse from R Wharfe to Upper Humber (GB104027064270)
- Outlet location
- SE5970034860 (OS grid reference) · View on Apple Maps
- EA ID / permit
- YWS00406 · 27/24/0228 · company name: WISTOW/STW
How the estimate works
- Dry-weather flow (DWF) = population × water use per person × (1 + infiltration). Water use is 136.5 L per person per day, England's per-capita consumption for 2024-25 [EA]. Infiltration of groundwater into sewers is taken as 0-40% of that flow [Escritt, via HBF]. The Environment Agency defines DWF as PG + I + E [EA].
- Population. The size of each works comes from the load entering it as reported under the Urban Waste Water Treatment Directive, in population equivalents (1 p.e. = 60 g of BOD a day) [UWWTD]. We treat population equivalent as population. That overstates flow where trade effluent adds load, and no official source links the two. Works serving fewer than 2,000 p.e. are not reported, so their size has to be entered by hand.
- Low spill rate = DWF. This is the method used by Giakoumis & Voulvoulis (2026), which they note likely underestimates storm loads [G&V].
- High spill rate = Formula A − flow to full treatment = (DWF + 1360P) − 3DWF. This is the largest flow the permit expects the storm tanks to handle before it passes on to treatment or overflows [EA]. The central rate is the geometric mean of the low and high rates.
- Volume = spill rate × hours spilling, with hours taken from the event duration monitor.
- Pollution = volume × published storm-sewage concentrations [Botturi et al.] [US EPA]. Organic load is also shown as person-days of untreated sewage at 60 g of BOD per person per day [UWWTD].
What this cannot tell you. It gives no real flow for any single spill, and no effect on the river or sea, which depends on the flow, tide and the other pressures on the water at the time. It gives no figure for spills from overflows on the sewer network, which serve catchments of unknown size. It is a way to put hours into rough physical terms, not a substitute for flow monitoring.
Sources
- EA: Water companies - environmental permits for storm overflows and emergency overflows
- EA: Water resources 2024 to 2025 - per capita consumption
- HBF: Foul sewer design - historic conventions (citing Escritt 1984 on infiltration)
- Giakoumis & Voulvoulis (2026), Environ. Sci.: Water Res. Technol., doi:10.1039/D5EW00860C
- Botturi et al. (2021), Crit. Rev. Environ. Sci. Technol. 51:1585 - CSO quality review, Table 2
- US EPA (2004) Report to Congress on CSOs and SSOs, chapter 4
- Urban Waste Water Treatment Directive, Article 2(6): 1 p.e. = 60 g BOD5/day
- Olympic-size swimming pool: 2,500 m³ at the nominal 2 m depth
← All Yorkshire Water works · Contains Environment Agency data licensed under the Open Government Licence v3.0. Spill start and stop times: © Environment Agency copyright and/or database right 2026. All rights reserved. They are water-company data and have not been verified by the Environment Agency. Works size: EEA Waterbase UWWTD. How to read the data.