A packaged plant room is designed twice: once as a process and once as a load. Every 100 mm added to its width or height, and every tonne of ballast, concrete or stored chemical shipped inside it, moves the module through a sequence of legal thresholds that add police notices, attendants, route surveys and days of lead time, or rule the route out altogether at a low bridge. This guide sets out the Construction and Use limits, the Special Types Order categories, the ESDAL notification process, the headroom rules in DMRB CD 127, and the module dimensions that follow from them.

The normal limits: Construction and Use and Authorised Weight

Any vehicle and load that fits within the Road Vehicles (Construction and Use) Regulations 1986 and the Road Vehicles (Authorised Weight) Regulations 1998 travels without notice to anyone. Regulation 8 caps the width of a motor vehicle or trailer at 2.55 m (2.6 m for refrigerated bodies); regulation 7 caps a rigid vehicle at 12 m, an articulated vehicle at 16.5 m with a 13.6 m semi-trailer, and a drawbar combination at 18.75 m. No general height limit exists except 4.57 m for buses, but regulation 10 requires a cab notice of the travelling height whenever it exceeds 3 m, and regulation 10(4) only exempts journeys on which every structure clears the vehicle by at least a metre. Weight under the 1998 Regulations tops out at 44,000 kg for a six-axle articulated combination with road-friendly suspension and a drive axle of no more than 10,500 kg, 40,000 kg on five axles and 38,000 kg on four; a kingpin-to-rear-axle check of 5,500 kg per metre can bite on short trailers.

Loads wider than the vehicle are allowed under regulation 82, with conditions that escalate with width and length:

Dimension (vehicle plus load)RegimeRequirement
Width up to 2.9 m, lateral projection under 305 mm each sideC&UNone
Width over 2.9 m up to 3.5 mC&U reg 82 and Schedule 12Indivisible load; 2 clear working days’ notice to police for each force area
Width over 3.5 m up to 4.3 mC&U reg 82 and Schedule 12As above plus an attendant
Width over 4.3 m up to 5.0 mSTGO 2003 art 15Police notice, attendant, special types vehicle
Width over 5.0 m up to 6.1 mSTGO art 15(5), Schedule 7Written consent of the Secretary of State (form VR1) before the journey
Width over 6.1 m, rigid length over 30 m or weight over 150 tSpecial OrderIndividual order from National Highways; 5 days to road and bridge authorities, 2 to police
Rigid length (vehicle and load) over 18.65 m, or combination over 25.9 mC&U reg 82(4) / STGO art 12Police notice and attendant; C&U ceiling 27.4 m

Notification periods are two clear working days, excluding Sundays and bank holidays, and the notice must state the time, date and route and the dimensions of each vehicle and projection. Police forces may accept less at their discretion but seldom do for first-time movements.

Special types: STGO categories and weight

Loads that cannot be carried within the Authorised Weight Regulations move under the Road Vehicles (Authorisation of Special Types) (General) Order 2003 as abnormal indivisible loads. Three categories apply, each requiring a plate on the tractor and its own speed limits:

  • Category 1: up to 46,000 kg on five axles or 50,000 kg on six, with axle weights within the normal regulations; 60/50/40 mph on motorway, dual carriageway and other roads.
  • Category 2: up to 80,000 kg on at least six axles, 12,500 kg per axle; 40/35/30 mph.
  • Category 3: up to 150,000 kg, 16,500 kg per axle; 40/35/30 mph.

Article 17 requires notice to every road and bridge authority on the route, with a signed indemnity for damage, whenever the gross weight exceeds 44,000 kg or axle weights exceed the Authorised Weight Schedule 3 limits; the period is two working days for Categories 1 and 2 and five for Category 3. Above 80,000 kg the police must also be notified. Most packaged plant movements that leave the normal regime do so on weight rather than width: a 14 m plant room with internal tanks and a concrete floor slab can reach 40 t, which on a 17 t tractor and step-frame trailer gives a 57 t train and a Category 2 movement even though the width may be within 3 m.

ESDAL and the notification workflow

National Highways’ Electronic Service Delivery for Abnormal Loads (ESDAL) is the online system through which hauliers plan a route and notify police, highway authorities and structure owners in one submission. A load is notifiable through ESDAL when it exceeds 44,000 kg, 2.9 m width or 18.65 m rigid length. ESDAL holds the structures database, flags bridges whose assessed capacity or headroom is below the proposed load, and returns objections or conditions from each authority. Lead time in practice is a week for a routine Category 1 or 2 movement on a known route and several weeks where a bridge owner (Network Rail, a canal trust or a local authority with a weak structure) has to assess the load individually. Special orders for loads above the STGO ceilings take months and are costed in tens of thousands of pounds once escorts and traffic management are included.

Escorting is a matter of police policy rather than statute. Since 2010 the police have withdrawn from most routine escorts, and self-escort by trained private escort vehicles is normal for loads above 3.5 m wide or 25.9 m long. Movements above 5 m wide or 100 t often still require police presence, dictated in the ESDAL response, with the cost recoverable from the haulier.

Height: no law, but a bridge

Height is governed by structures, not by the regulations. Design Manual for Roads and Bridges CD 127 sets the headroom at new overbridges on motorways and trunk roads at 5.30 m plus a sag-curve allowance of up to 80 mm, and the maintained headroom, the minimum to be preserved at all times, at 5.03 m; footbridges, sign gantries and other structures vulnerable to impact get 5.70 m new and 5.41 m maintained, and structures on designated high load routes 6.45 m. Those figures apply to the strategic network. Local roads carry thousands of older arch and rail bridges with signed headroom of 3.5 to 4.5 m, and railway bridges below 4.95 m (16 ft 3 in) must be signed, which is why 4.95 m has become the unofficial threshold between a routine movement and one needing a detailed height survey. Regulation 10 requires the cab notice in feet and inches, and the driver must plan to avoid any structure that does not clear the travelling height by a metre unless a documented route is carried.

Travelling height is the module height plus the trailer deck: about 1.35 m for a flat trailer, 0.95 to 1.0 m for a step-frame and 0.5 to 0.6 m for a low loader. A 3.0 m high module on a step-frame travels at 4.0 m and goes almost anywhere; a 3.5 m module on the same trailer travels at 4.5 m and starts to meet signed bridges on B roads; a 4.0 m module needs a low loader to stay under 4.6 m and will still need a route survey. Overhead power lines are the other constraint: distribution network operators ask to be told of loads over 5.2 m under 11 kV and 33 kV lines, and many rural site accesses have lower crossings than the public road.

What the thresholds mean for module sizing

Working back from the law gives a hierarchy of preferred module envelopes:

Envelope (L × W × H, mass)Transport regimeComment
12.19 × 2.44 × 2.90 m, up to 26 t (40 ft high-cube container)Normal C&U, any haulierCheapest and most flexible; internal width 2.35 m limits two-sided access to equipment
13.6 × 2.9 × 3.0 m, up to 27 tNormal C&U on a step-frameFull semi-trailer length and the maximum unnotified width; the usual plant room envelope
13.6 × 3.5 × 3.2 m, up to 27 tC&U wide load, police notice, no attendantTwo working days’ notice; modest haulage premium
16 × 4.3 × 3.6 m, up to 60 tC&U width ceiling with attendant; STGO Cat 2 on weightESDAL notification to all authorities, escort vehicle, 30 to 40 mph; route survey for height
Over 4.3 m wide or 60 tSTGO Cat 2 or 3, VR1 above 5 mWeeks of lead time; bridge assessments; often cheaper to split the module

Worked example. A proposed plant room is 14.0 × 3.6 × 3.4 m and 38 t with its filters, pipework and a cast floor. Width 3.6 m exceeds 3.5 m, so police notice and an attendant are needed; the train weight of about 55 t makes it STGO Category 2, with ESDAL notification and indemnities to every highway and bridge authority on the route and a 40 mph motorway limit; the travelling height of 4.4 m on a step-frame requires a route survey and a cab notice; the 14 m load overhangs a 13.6 m trailer by 0.4 m, within the rear projection rules. Splitting the same plant into two modules of 7.0 × 3.0 × 3.0 m at 19 t each brings both inside the normal regulations except for a 3.0 m width, which needs police notice only; each travels at 4.0 m on a step-frame and at 44 t gross on a standard tractor unit. Reconnecting pipework, cabling and cladding at the site joint costs perhaps two days of fitting, against a haulage saving that typically runs to several thousand pounds per movement and, more importantly, removes the programme risk of a refused route.

Design rules that follow: keep width at 2.9 or 3.5 m rather than 3.0 or 3.6 m, because the thresholds, not the round numbers, set the cost; put the split line through a corridor rather than through a tank; ship tanks empty and ballast on site; keep the centre of gravity low and recorded on the lifting plan, since a top-heavy module forces a low loader for stability before it does for height; and check the site access, not only the public highway, for the last 200 m of bends, gradients and overhead services. For the plant room designs themselves and how envelopes are chosen for different process trains, see the packaged plant rooms page.

Pitfalls

  • Measuring the module, not the load. Width is measured over the widest point including cladding flashings, lifting lugs, door handles and eaves gutters; a 2.9 m module with 60 mm gutters is a 3.02 m load.
  • Ignoring the lateral projection rule. A 2.55 m trailer carrying a 3.0 m module has 225 mm projections each side, under the 305 mm limit, but the overall width still exceeds 2.9 m and triggers notice.
  • Assuming Scotland and Wales match. Trunk road authorities differ (Transport Scotland, Welsh Government), ESDAL covers England, Scotland and Wales but local police procedures vary, and Northern Ireland has its own abnormal load regime.
  • Forgetting the crane. A 38 t module lifted at 12 m radius needs a 200 to 250 t mobile crane, itself an STGO Category 2 or 3 movement with its own notifications and ground bearing requirements.
  • Chemical inventories. Modules shipped with dosing chemicals on board bring the carriage of dangerous goods regulations into play; ship them empty.

Frequently asked questions

What is the maximum width of a load on UK roads without notification?

2.9 m overall, including the load, provided no lateral projection exceeds 305 mm. Between 2.9 and 3.5 m the police must receive two clear working days’ notice; between 3.5 and 4.3 m an attendant is also required; above 4.3 m the movement falls under the Special Types General Order, and above 5 m it needs written consent from the Secretary of State.

When does a packaged plant movement need ESDAL notification?

When the gross train weight exceeds 44,000 kg, the overall width exceeds 2.9 m or the rigid length exceeds 18.65 m. Most plant rooms over 12 m long cross the weight threshold before the width one, which brings the Special Types Order and notifications to every road and bridge authority on the route.

Is there a legal height limit for road vehicles in the UK?

No general limit exists apart from 4.57 m for buses. Height is controlled by structures: new trunk road overbridges are built at 5.3 m and maintained at 5.03 m under CD 127, but many local road and rail bridges are signed at 3.5 to 4.5 m. Any vehicle over 3 m high must carry a cab height notice, and loads over about 4.95 m travelling height need a detailed route survey.

What is the best module size for a packaged plant room?

Up to 13.6 m long, 2.9 m wide, 3.0 m high and 27 t travels under normal regulations on a step-frame trailer. Going to 3.5 m wide adds only a police notice; going to 3.6 m adds an attendant, and going above about 27 t payload moves the load into STGO Category 2. Splitting a large plant into two notifiable but non-STGO modules is usually cheaper and lower risk than one abnormal load.