Storm overflow register · Anglian Water

Marston sewage works: storm overflow spills 2025

Marston sewage treatment works, run by Anglian Water, has 1 monitored storm overflow discharging to The River Witham. In 2025 it recorded 16 spills totalling 162 hours, against 54 spills and 808 hours in 2024. By hours spilling, it ranks 126 of 419 Anglian Water works, where 1 spilled longest.

Works size: 66,420 population equivalent (GRANTHAM STW, UWWTD 2018). Used for the spill volume estimate.

Every spill in 2025

Each blue mark is one spill, placed by when it started and sized by how long it lasted. Hover over a mark for the date and duration.

JanFebMarAprMayJunJulAugSepOctNovDecMarston (Grantham) WRC5 Jan 2025 19:44 GMT, 4.3 h6 Jan 2025 00:00 GMT, 24 h7 Jan 2025 00:00 GMT, 24 h8 Jan 2025 00:00 GMT, 24 h9 Jan 2025 00:00 GMT, 36 min28 May 2025 09:44 GMT, 86 min6 Jul 2025 21:56 GMT, 2.1 h7 Jul 2025 00:00 GMT, 6.1 h14 Nov 2025 11:38 GMT, 12.4 h15 Nov 2025 00:00 GMT, 24 h16 Nov 2025 00:00 GMT, 2.9 h16 Nov 2025 02:54 GMT, 2 min29 Nov 2025 13:34 GMT, 7.5 h29 Nov 2025 21:06 GMT, 2 min29 Nov 2025 21:22 GMT, 4 min29 Nov 2025 21:26 GMT, 2 min29 Nov 2025 21:30 GMT, 2 min29 Nov 2025 21:32 GMT, 2 min29 Nov 2025 21:34 GMT, 2 min29 Nov 2025 23:16 GMT, 44 min30 Nov 2025 00:00 GMT, 3 h4 Dec 2025 19:36 GMT, 4.4 h5 Dec 2025 00:00 GMT, 4 h5 Dec 2025 09:54 GMT, 16 min5 Dec 2025 10:10 GMT, 2 min5 Dec 2025 10:12 GMT, 2 min16 Dec 2025 10:16 GMT, 6.7 h18 Dec 2025 18:44 GMT, 5.3 h19 Dec 2025 00:00 GMT, 3.5 h19 Dec 2025 14:36 GMT, 34 min

Estimated spill volume by month, 2025

Hours spilling each month × the estimated spill rate for a works of this size. The bars are central estimates and the whiskers show the low–high range. Method.

0100k200k300kJan 2025: 77 h spilling ≈ 87,518 m³ (range 34,860–219,716 m³)JanFeb 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0–0.0 m³)FebMar 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0–0.0 m³)MarApr 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0–0.0 m³)AprMay 2025: 1.4 h spilling ≈ 1,593 m³ (range 635–4,000 m³)MayJun 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0–0.0 m³)JunJul 2025: 8.2 h spilling ≈ 9,332 m³ (range 3,717–23,429 m³)JulAug 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0–0.0 m³)AugSep 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0–0.0 m³)SepOct 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0–0.0 m³)OctNov 2025: 51 h spilling ≈ 57,814 m³ (range 23,028–145,144 m³)NovDec 2025: 25 h spilling ≈ 28,110 m³ (range 11,197–70,572 m³)Dec
Cubic metres (m³), estimate. Hours are measured by the event duration monitor.

Longest single spills

Started (GMT)OverflowDurationEstimated volume
15 Nov 2025, 00:00Marston (Grantham) WRC1.0 days10,880 – 68,572 m³
8 Jan 2025, 00:00Marston (Grantham) WRC1.0 days10,880 – 68,572 m³
7 Jan 2025, 00:00Marston (Grantham) WRC1.0 days10,880 – 68,572 m³
6 Jan 2025, 00:00Marston (Grantham) WRC1.0 days10,880 – 68,572 m³
14 Nov 2025, 11:38Marston (Grantham) WRC12.4 h5,606 – 35,334 m³

Estimated 2025 spill volume and pollution

Estimate, not a measurement. Monitors record how long an overflow spills, not how much. This calculator back-calculates a spill rate from the size of the works, using the Environment Agency's permit formulae, and multiplies it by published storm-sewage concentrations. How it works.

Volume, central estimate184,367 m³range 73,437 – 462,861 m³
In litres184.4 millionrange 73.4 million – 462.9 million L
Olympic swimming pools74at 2,500 m³ each
Organic load, as people's raw sewage276,551person-days of untreated BOD

Assumed spill rate while spilling: 125.9 – 793.7 L/s (central 316.1 L/s), from a dry-weather flow of 125.9 L/s.

Pollutant releasedLowCentralHighConcentration used (low / typical / high)
BOD₅ (organic load) 2,937 kg16,593 kg92,572 kg 40 / 90 / 200 mg/L
Low/high: Europe range, Ellis & Jenkins 2005; typical: UK, Ellis & Jenkins 2005 (both via botturi)
Suspended solids 7,711 kg78,356 kg333,723 kg 105 / 425 / 721 mg/L
Low/high: Europe range; typical: UK, Ellis & Jenkins 2005 (via botturi)
Ammonium-N 140 kg1,162 kg4,305 kg 1.9 / 6.3 / 9.3 mg/L
Low: Germany, Brombach 2005; typical/high: Paris range 3.3–9.3 midpoint and top, Gasperi 2012 (via botturi); no UK value found
Total phosphorus 88 kg479 kg2,499 kg 1.2 / 2.6 / 5.4 mg/L
Low/high: Paris, Gasperi 2012; typical: Slovakia (via botturi). UK figure of 10 mg/L treated as an outlier
E. coli 7.3 trillion organisms184.4 trillion organisms4.6 × 10¹⁵ organisms 10,000 / 100,000 / 1.0 million per 100 mL
Median range at CSO and retention-tank outlets, Stott et al. 2018 (via botturi); typical = log midpoint

Low combines the low spill rate with low concentrations, and high combines high with high, so the true figure is very likely inside the range. Long spills become more diluted as they go on, so the central figure tends to overstate the load of long events. The calculator does not estimate the effect on the receiving water, which depends on river flow or tide at the time of the spill.

Marston (Grantham) WRC

Storm tank at sewage works · discharges to The River Witham

Spills 2025
16 (162 hours) · down 70% on 2024
Spills 2024
54 (808 hours)
Long-term average
42.7 spills a year (monitored since 2023)
Monitor uptime
100% of the year
Investigation
Env Act (SODRP) investigation ongoing
Improvement
UWWTR improvement ongoing
WFD catchment
Witham - conf Cringle Bk to conf Brant (GB105030056780)
Outlet location
SK9087042860 (OS grid reference) · View on Apple Maps
EA ID / permit
AWS00822 · ANNNF10436 · company name: MARSTON STW (LINCS)

How the estimate works

  1. Dry-weather flow (DWF) = population × water use per person × (1 + infiltration). Water use is 136.5 L per person per day, England's per-capita consumption for 2024–25 [EA]. Infiltration of groundwater into sewers is taken as 0–40% of that flow [Escritt, via HBF]. The Environment Agency defines DWF as PG + I + E [EA].
  2. Population. The size of each works comes from the load entering it as reported under the Urban Waste Water Treatment Directive, in population equivalents (1 p.e. = 60 g of BOD a day) [UWWTD]. We treat population equivalent as population. That overstates flow where trade effluent adds load, and no official source links the two. Works serving fewer than 2,000 p.e. are not reported, so their size has to be entered by hand.
  3. Low spill rate = DWF. This is the method used by Giakoumis & Voulvoulis (2026), which they note likely underestimates storm loads [G&V].
  4. High spill rate = Formula A − flow to full treatment = (DWF + 1360P) − 3DWF. This is the largest flow the permit expects the storm tanks to handle before it passes on to treatment or overflows [EA]. The central rate is the geometric mean of the low and high rates.
  5. Volume = spill rate × hours spilling, with hours taken from the event duration monitor.
  6. Pollution = volume × published storm-sewage concentrations [Botturi et al.] [US EPA]. Organic load is also shown as person-days of untreated sewage at 60 g of BOD per person per day [UWWTD].

What this cannot tell you. It gives no real flow for any single spill, and no effect on the river or sea, which depends on the flow, tide and the other pressures on the water at the time. It gives no figure for spills from overflows on the sewer network, which serve catchments of unknown size. It is a way to put hours into rough physical terms, not a substitute for flow monitoring.

Sources

  1. EA: Water companies – environmental permits for storm overflows and emergency overflows
  2. EA: Water resources 2024 to 2025 – per capita consumption
  3. HBF: Foul sewer design – historic conventions (citing Escritt 1984 on infiltration)
  4. Giakoumis & Voulvoulis (2026), Environ. Sci.: Water Res. Technol., doi:10.1039/D5EW00860C
  5. Botturi et al. (2021), Crit. Rev. Environ. Sci. Technol. 51:1585 – CSO quality review, Table 2
  6. US EPA (2004) Report to Congress on CSOs and SSOs, chapter 4
  7. Urban Waste Water Treatment Directive, Article 2(6): 1 p.e. = 60 g BOD5/day
  8. Olympic-size swimming pool: 2,500 m³ at the nominal 2 m depth

← All Anglian Water works · Contains Environment Agency data licensed under the Open Government Licence v3.0. Spill start and stop times: © Environment Agency copyright and/or database right 2026. All rights reserved. They are water-company data and have not been verified by the Environment Agency. Works size: EEA Waterbase UWWTD. How to read the data.