Storm overflow register · Anglian Water

Shotley sewage works: storm overflow spills 2025

Shotley sewage treatment works, run by Anglian Water, has 1 monitored storm overflow discharging to River Orwell T. In 2025 it recorded 4 spills totalling 2.5 hours, against 8 spills and 2.5 hours in 2024. By hours spilling, it ranks 350 of 419 Anglian Water works, where 1 spilled longest.

Every spill in 2025

Each blue mark is one spill, placed by when it started and sized by how long it lasted. Hover over a mark for the date and duration.

JanFebMarAprMayJunJulAugSepOctNovDecShotley STW21 Jul 2025 06:12 GMT, 36 min21 Jul 2025 06:48 GMT, 2 min21 Jul 2025 06:52 GMT, 2 min21 Jul 2025 06:56 GMT, 2 min21 Jul 2025 06:58 GMT, 2 min21 Jul 2025 07:00 GMT, 10 min21 Jul 2025 07:12 GMT, 4 min21 Jul 2025 07:18 GMT, 2 min21 Jul 2025 07:20 GMT, 2 min21 Jul 2025 07:26 GMT, 2 min21 Jul 2025 07:30 GMT, 4 min21 Jul 2025 07:34 GMT, 2 min21 Jul 2025 07:36 GMT, 8 min21 Jul 2025 07:44 GMT, 2 min21 Jul 2025 07:46 GMT, 2 min21 Jul 2025 07:48 GMT, 6 min21 Jul 2025 07:54 GMT, 6 min21 Jul 2025 08:00 GMT, 10 min21 Jul 2025 08:14 GMT, 2 min21 Jul 2025 09:36 GMT, 2 min3 Aug 2025 17:46 GMT, 18 min3 Aug 2025 18:04 GMT, 4 min3 Aug 2025 18:08 GMT, 2 min3 Aug 2025 18:10 GMT, 2 min13 Sep 2025 15:28 GMT, 16 min23 Oct 2025 08:22 GMT, 2 min

Hours spilling by month, 2025

00.511.52Jan 2025: 0.0 hours spillingJanFeb 2025: 0.0 hours spillingFebMar 2025: 0.0 hours spillingMarApr 2025: 0.0 hours spillingAprMay 2025: 0.0 hours spillingMayJun 2025: 0.0 hours spillingJunJul 2025: 1.8 hours spillingJulAug 2025: 0.4 hours spillingAugSep 2025: 0.3 hours spillingSepOct 2025: 0.0 hours spillingOctNov 2025: 0.0 hours spillingNovDec 2025: 0.0 hours spillingDec
Hours, measured by the event duration monitor.

Longest single spills

Started (GMT)OverflowDuration
21 Jul 2025, 06:12Shotley STW0.6 h
3 Aug 2025, 17:46Shotley STW0.3 h
13 Sep 2025, 15:28Shotley STW0.3 h
21 Jul 2025, 08:00Shotley STW0.2 h
21 Jul 2025, 07:00Shotley STW0.2 h

Estimated 2025 spill volume and pollution

Estimate, not a measurement. Monitors record how long an overflow spills, not how much. This calculator back-calculates a spill rate from the size of the works, using the Environment Agency's permit formulae, and multiplies it by published storm-sewage concentrations. How it works.

This works serves fewer than 2,000 people, or was not matched to a UWWTD report, so its size is not published. The population equivalent above is a placeholder of 1,000. Enter the population served if you know it.

Volume, central estimate43 m³range 17 – 108 m³
In litres42,836range 17,063 – 107,542 L
Olympic swimming pools0.0at 2,500 m³ each
Organic load, as people's raw sewage64person-days of untreated BOD

Assumed spill rate while spilling: 1.9 – 11.9 L/s (central 4.8 L/s), from a dry-weather flow of 1.9 L/s.

Pollutant releasedLowCentralHighConcentration used (low / typical / high)
BOD₅ (organic load) 0.7 kg3.9 kg22 kg 40 / 90 / 200 mg/L
Low/high: Europe range, Ellis & Jenkins 2005; typical: UK, Ellis & Jenkins 2005 (both via botturi)
Suspended solids 1.8 kg18 kg78 kg 105 / 425 / 721 mg/L
Low/high: Europe range; typical: UK, Ellis & Jenkins 2005 (via botturi)
Ammonium-N 0.0 kg0.3 kg1.0 kg 1.9 / 6.3 / 9.3 mg/L
Low: Germany, Brombach 2005; typical/high: Paris range 3.3–9.3 midpoint and top, Gasperi 2012 (via botturi); no UK value found
Total phosphorus 0.0 kg0.1 kg0.6 kg 1.2 / 2.6 / 5.4 mg/L
Low/high: Paris, Gasperi 2012; typical: Slovakia (via botturi). UK figure of 10 mg/L treated as an outlier
E. coli 1.7 billion organisms42.8 billion organisms1.1 trillion organisms 10,000 / 100,000 / 1.0 million per 100 mL
Median range at CSO and retention-tank outlets, Stott et al. 2018 (via botturi); typical = log midpoint

Low combines the low spill rate with low concentrations, and high combines high with high, so the true figure is very likely inside the range. Long spills become more diluted as they go on, so the central figure tends to overstate the load of long events. The calculator does not estimate the effect on the receiving water, which depends on river flow or tide at the time of the spill.

Shotley STW

Inlet overflow at sewage works · discharges to River Orwell T

Spills 2025
4 (2.5 hours) · down 50% on 2024
Spills 2024
8 (2.5 hours)
Long-term average
8.2 spills a year (monitored since 2021)
Monitor uptime
100% of the year
Investigation
Env Act (SODRP) investigation ongoing, Bathing Water and/or Shellfish Water investigation ongoing
Improvement
No improvement action in reporting period
WFD catchment
ORWELL (GB520503613601)
Outlet location
TM2498035140 (OS grid reference) · View on Apple Maps
EA ID / permit
AWS01128 · ASETS1532 · company name: SHOTLEY-OVERHALL FM STW

How the estimate works

  1. Dry-weather flow (DWF) = population × water use per person × (1 + infiltration). Water use is 136.5 L per person per day, England's per-capita consumption for 2024–25 [EA]. Infiltration of groundwater into sewers is taken as 0–40% of that flow [Escritt, via HBF]. The Environment Agency defines DWF as PG + I + E [EA].
  2. Population. The size of each works comes from the load entering it as reported under the Urban Waste Water Treatment Directive, in population equivalents (1 p.e. = 60 g of BOD a day) [UWWTD]. We treat population equivalent as population. That overstates flow where trade effluent adds load, and no official source links the two. Works serving fewer than 2,000 p.e. are not reported, so their size has to be entered by hand.
  3. Low spill rate = DWF. This is the method used by Giakoumis & Voulvoulis (2026), which they note likely underestimates storm loads [G&V].
  4. High spill rate = Formula A − flow to full treatment = (DWF + 1360P) − 3DWF. This is the largest flow the permit expects the storm tanks to handle before it passes on to treatment or overflows [EA]. The central rate is the geometric mean of the low and high rates.
  5. Volume = spill rate × hours spilling, with hours taken from the event duration monitor.
  6. Pollution = volume × published storm-sewage concentrations [Botturi et al.] [US EPA]. Organic load is also shown as person-days of untreated sewage at 60 g of BOD per person per day [UWWTD].

What this cannot tell you. It gives no real flow for any single spill, and no effect on the river or sea, which depends on the flow, tide and the other pressures on the water at the time. It gives no figure for spills from overflows on the sewer network, which serve catchments of unknown size. It is a way to put hours into rough physical terms, not a substitute for flow monitoring.

Sources

  1. EA: Water companies – environmental permits for storm overflows and emergency overflows
  2. EA: Water resources 2024 to 2025 – per capita consumption
  3. HBF: Foul sewer design – historic conventions (citing Escritt 1984 on infiltration)
  4. Giakoumis & Voulvoulis (2026), Environ. Sci.: Water Res. Technol., doi:10.1039/D5EW00860C
  5. Botturi et al. (2021), Crit. Rev. Environ. Sci. Technol. 51:1585 – CSO quality review, Table 2
  6. US EPA (2004) Report to Congress on CSOs and SSOs, chapter 4
  7. Urban Waste Water Treatment Directive, Article 2(6): 1 p.e. = 60 g BOD5/day
  8. Olympic-size swimming pool: 2,500 m³ at the nominal 2 m depth

← All Anglian Water works · Contains Environment Agency data licensed under the Open Government Licence v3.0. Spill start and stop times: © Environment Agency copyright and/or database right 2026. All rights reserved. They are water-company data and have not been verified by the Environment Agency. Works size: EEA Waterbase UWWTD. How to read the data.