Storm overflow register · Severn Trent Water

Newthorpe sewage works: storm overflow spills 2025

Newthorpe sewage treatment works, run by Severn Trent Water, has 2 monitored storm overflows discharging to Gilt Brook. In 2025 they recorded 89 spills totalling 551 hours, against 139 spills and 1,339 hours in 2024. By hours spilling, it ranks 76 of 435 Severn Trent Water works, where 1 spilled longest.

Works size: 47,338 population equivalent (NEWTHORPE STW, UWWTD 2018). Used for the spill volume estimate.

Every spill in 2025

Each blue mark is one spill, placed by when it started and sized by how long it lasted. Hover over a mark for the date and duration.

JanFebMarAprMayJunJulAugSepOctNovDecNewthorpe Sewage…3 spills, 7.4 h, 1 Jan to 1 Jan5 Jan 2025 09:31 GMT, 9.8 h2 spills, 10.4 h, 7 Jan to 7 Jan6 spills, 19.9 h, 27 Jan to 28 Jan8 spills, 12.2 h, 27 May to 28 May3 Sep 2025 16:20 GMT, 2.3 h4 Sep 2025 13:02 GMT, 3.3 h14 Sep 2025 18:19 GMT, 4.7 h17 Sep 2025 07:35 GMT, 8.8 h2 spills, 7 h, 20 Sep to 21 Sep3 Oct 2025 15:47 GMT, 7.5 h19 Oct 2025 20:49 GMT, 5.9 h4 Nov 2025 21:02 GMT, 7.3 h3 spills, 36.1 h, 10 Nov to 13 Nov14 Nov 2025 06:04 GMT, 8 h16 Nov 2025 08:50 GMT, 6 h4 spills, 13.1 h, 18 Nov to 19 Nov2 spills, 17.2 h, 22 Nov to 23 Nov29 Nov 2025 06:03 GMT, 7 h3 spills, 34.7 h, 30 Nov to 2 Dec2 spills, 8.3 h, 4 Dec to 4 Dec3 spills, 9.7 h, 5 Dec to 6 Dec2 spills, 8 h, 7 Dec to 7 Dec2 spills, 9.6 h, 9 Dec to 10 Dec2 spills, 36.2 h, 15 Dec to 17 Dec5 spills, 13 h, 17 Dec to 18 Dec2 spills, 12.8 h, 21 Dec to 22 DecNewthorpe Sewage…2 spills, 9.5 h, 1 Jan to 1 Jan5 Jan 2025 07:21 GMT, 12 h3 spills, 1.8 h, 7 Jan to 7 Jan2 spills, 11.7 h, 27 Jan to 28 Jan20 Feb 2025 16:50 GMT, 29 min24 May 2025 01:25 GMT, 2.3 h6 spills, 11.8 h, 27 May to 28 May5 Jun 2025 16:06 GMT, 55 min4 spills, 5.7 h, 6 Jul to 7 Jul15 Jul 2025 12:51 GMT, 47 min2 spills, 1.5 h, 20 Jul to 20 Jul2 spills, 7.8 h, 3 Sep to 4 Sep11 Sep 2025 12:52 GMT, 27 min2 spills, 5.5 h, 14 Sep to 14 Sep17 Sep 2025 05:18 GMT, 8.9 h20 Sep 2025 19:37 GMT, 7.3 h2 spills, 6.2 h, 3 Oct to 3 Oct19 Oct 2025 19:03 GMT, 6.7 h23 Oct 2025 01:26 GMT, 84 min29 Oct 2025 05:54 GMT, 43 min4 Nov 2025 18:55 GMT, 7.8 h7 spills, 16.9 h, 10 Nov to 12 Nov14 Nov 2025 04:12 GMT, 9.9 h2 spills, 9 h, 18 Nov to 19 Nov2 spills, 9.7 h, 22 Nov to 23 Nov2 spills, 10 h, 28 Nov to 29 Nov2 spills, 11.7 h, 1 Dec to 2 Dec2 spills, 0.7 h, 4 Dec to 4 Dec5 Dec 2025 18:36 GMT, 104 min7 Dec 2025 14:10 GMT, 85 min9 Dec 2025 03:42 GMT, 9.1 h7 spills, 21.7 h, 15 Dec to 16 Dec2 spills, 6.6 h, 17 Dec to 18 Dec21 Dec 2025 21:05 GMT, 5 h

Estimated spill volume by month, 2025

Hours spilling each month × the estimated spill rate for a works of this size. The bars are central estimates and the whiskers show the low-high range. Method.

0100k200k300k400kJan 2025: 83 h spilling ≈ 66,917 m³ (range 26,654-167,997 m³)JanFeb 2025: 0.5 h spilling ≈ 406 m³ (range 162-1,018 m³)FebMar 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0-0.0 m³)MarApr 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0-0.0 m³)AprMay 2025: 26 h spilling ≈ 21,332 m³ (range 8,497-53,555 m³)MayJun 2025: 0.9 h spilling ≈ 730 m³ (range 291-1,833 m³)JunJul 2025: 8.0 h spilling ≈ 6,489 m³ (range 2,585-16,291 m³)JulAug 2025: 0.0 h spilling ≈ 0.0 m³ (range 0.0-0.0 m³)AugSep 2025: 56 h spilling ≈ 45,341 m³ (range 18,060-113,830 m³)SepOct 2025: 28 h spilling ≈ 22,954 m³ (range 9,143-57,628 m³)OctNov 2025: 163 h spilling ≈ 131,886 m³ (range 52,533-331,106 m³)NovDec 2025: 185 h spilling ≈ 150,380 m³ (range 59,899-377,534 m³)Dec
Cubic metres (m³), estimate. Hours are measured by the event duration monitor.

Longest single spills

Started (GMT)OverflowDurationEstimated volume
15 Dec 2025, 14:18Newthorpe Sewage Treatment Works1.4 days10,931 - 68,896 m³
1 Dec 2025, 07:54Newthorpe Sewage Treatment Works1.2 days9,219 - 58,103 m³
11 Nov 2025, 23:04Newthorpe Sewage Treatment Works1.0 days8,056 - 50,772 m³
23 Nov 2025, 06:35Newthorpe Sewage Treatment Works15.7 h5,083 - 32,038 m³
5 Jan 2025, 07:21Newthorpe Sewage Treatment Works12.0 h3,872 - 24,402 m³

Estimated 2025 spill volume and pollution

Estimate, not a measurement. Monitors record how long an overflow spills, not how much. This calculator back-calculates a spill rate from the size of the works, using the Environment Agency's permit formulae, and multiplies it by published storm-sewage concentrations. How it works.

Volume, central estimate446,597 m³range 177,889 - 1.1 million m³
In litres446.6 millionrange 177.9 million - 1.1 billion L
Olympic swimming pools179at 2,500 m³ each
Organic load, as people's raw sewage669,896person-days of untreated BOD

Assumed spill rate while spilling: 89.7 - 565.6 L/s (central 225.3 L/s), from a dry-weather flow of 89.7 L/s.

Pollutant releasedLowCentralHighConcentration used (low / typical / high)
BOD₅ (organic load) 7,116 kg40,194 kg224,240 kg 40 / 90 / 200 mg/L
Low/high: Europe range, Ellis & Jenkins 2005; typical: UK, Ellis & Jenkins 2005 (both via botturi)
Suspended solids 18,678 kg189,804 kg808,385 kg 105 / 425 / 721 mg/L
Low/high: Europe range; typical: UK, Ellis & Jenkins 2005 (via botturi)
Ammonium-N 338 kg2,814 kg10,427 kg 1.9 / 6.3 / 9.3 mg/L
Low: Germany, Brombach 2005; typical/high: Paris range 3.3-9.3 midpoint and top, Gasperi 2012 (via botturi); no UK value found
Total phosphorus 213 kg1,161 kg6,054 kg 1.2 / 2.6 / 5.4 mg/L
Low/high: Paris, Gasperi 2012; typical: Slovakia (via botturi). UK figure of 10 mg/L treated as an outlier
E. coli 17.8 trillion organisms446.6 trillion organisms1.1 × 10¹⁶ organisms 10,000 / 100,000 / 1.0 million per 100 mL
Median range at CSO and retention-tank outlets, Stott et al. 2018 (via botturi); typical = log midpoint

Low combines the low spill rate with low concentrations, and high combines high with high, so the true figure is very likely inside the range. Long spills become more diluted as they go on, so the central figure tends to overstate the load of long events. The calculator does not estimate the effect on the receiving water, which depends on river flow or tide at the time of the spill.

Newthorpe Sewage Treatment Works

Storm tank at sewage works · discharges to Gilt Brook

Spills 2025
42 (326 hours) · down 39% on 2024
Spills 2024
69 (767 hours)
Long-term average
64.8 spills a year (monitored since 2021)
Monitor uptime
100% of the year
High-spill reason (company)
Not asset maintenance - Hydraulic capacity
Investigation
Env Act (SODRP) investigation ongoing, UWWTR investigation ongoing, Operational investigation completed
Improvement
Operational improvement completed
WFD catchment
Gilt Brook Catchment (trib of Erewash) (GB104028052570)
Outlet location
SK4777144650 (OS grid reference) · View on Apple Maps
EA ID / permit
SVT01645 · T/61/45995/R · company name: NEWTHORPE STW (SSTO)

Newthorpe Sewage Treatment Works

Inlet overflow at sewage works · discharges to Gilt Brook

Spills 2025
47 (225 hours) · down 33% on 2024
Spills 2024
70 (572 hours)
Long-term average
53.0 spills a year (monitored since 2021)
Monitor uptime
100% of the year
High-spill reason (company)
Not asset maintenance - Hydraulic capacity
Investigation
Env Act (SODRP) investigation ongoing, UWWTR investigation ongoing, Operational investigation completed
Improvement
No improvement action in reporting period
WFD catchment
Gilt Brook Catchment (trib of Erewash) (GB104028052570)
Outlet location
SK4777144650 (OS grid reference) · View on Apple Maps
EA ID / permit
SVT01644 · T/61/45995/R · company name: NEWTHORPE STW (CSO&EO)

How the estimate works

  1. Dry-weather flow (DWF) = population × water use per person × (1 + infiltration). Water use is 136.5 L per person per day, England's per-capita consumption for 2024-25 [EA]. Infiltration of groundwater into sewers is taken as 0-40% of that flow [Escritt, via HBF]. The Environment Agency defines DWF as PG + I + E [EA].
  2. Population. The size of each works comes from the load entering it as reported under the Urban Waste Water Treatment Directive, in population equivalents (1 p.e. = 60 g of BOD a day) [UWWTD]. We treat population equivalent as population. That overstates flow where trade effluent adds load, and no official source links the two. Works serving fewer than 2,000 p.e. are not reported, so their size has to be entered by hand.
  3. Low spill rate = DWF. This is the method used by Giakoumis & Voulvoulis (2026), which they note likely underestimates storm loads [G&V].
  4. High spill rate = Formula A − flow to full treatment = (DWF + 1360P) − 3DWF. This is the largest flow the permit expects the storm tanks to handle before it passes on to treatment or overflows [EA]. The central rate is the geometric mean of the low and high rates.
  5. Volume = spill rate × hours spilling, with hours taken from the event duration monitor.
  6. Pollution = volume × published storm-sewage concentrations [Botturi et al.] [US EPA]. Organic load is also shown as person-days of untreated sewage at 60 g of BOD per person per day [UWWTD].

What this cannot tell you. It gives no real flow for any single spill, and no effect on the river or sea, which depends on the flow, tide and the other pressures on the water at the time. It gives no figure for spills from overflows on the sewer network, which serve catchments of unknown size. It is a way to put hours into rough physical terms, not a substitute for flow monitoring.

Sources

  1. EA: Water companies - environmental permits for storm overflows and emergency overflows
  2. EA: Water resources 2024 to 2025 - per capita consumption
  3. HBF: Foul sewer design - historic conventions (citing Escritt 1984 on infiltration)
  4. Giakoumis & Voulvoulis (2026), Environ. Sci.: Water Res. Technol., doi:10.1039/D5EW00860C
  5. Botturi et al. (2021), Crit. Rev. Environ. Sci. Technol. 51:1585 - CSO quality review, Table 2
  6. US EPA (2004) Report to Congress on CSOs and SSOs, chapter 4
  7. Urban Waste Water Treatment Directive, Article 2(6): 1 p.e. = 60 g BOD5/day
  8. Olympic-size swimming pool: 2,500 m³ at the nominal 2 m depth

← All Severn Trent Water works · Contains Environment Agency data licensed under the Open Government Licence v3.0. Spill start and stop times: © Environment Agency copyright and/or database right 2026. All rights reserved. They are water-company data and have not been verified by the Environment Agency. Works size: EEA Waterbase UWWTD. How to read the data.